Decision details

Extension of Term Maintenance Contracts

Decision status: Recommendations Approved

Is Key decision?: Yes

Is subject to call in?: Yes

Decisions:

For the reasons set out in the Cabinet Member’s report,

 

RESOLVED –

1.      That the Committee authorise a waiver of Contract Procedure Rules 5.6.1.2 as the initial contracts have been extended before.

2.   To allow extension of the following Term Maintenance Contracts for a further three months with the following Contractors:-

Kirkman and Jourdain Ltd. The extended value of this Building Maintenance contract with this company is £528,149 and the anticipated spend for the three month extension is £22,963 

D Long Construction Ltd. The extended value of this Building Maintenance contract with this company is £708,722 and the anticipated spend for the three month extension is £30,814 

Oakray Ltd, The extended value of the Mechanical Maintenance contract with this company is £1,074,474 and the anticipated spend for the three month extension is £46,716

T&D Barrs Ltd. The extended value of the Mechanical Maintenance contract with this company is £469,419 and the anticipated spend for the three month extension is £20,410 

Oakray Ltd. The extended value of the Electrical Maintenance Contract with this company is £769,977 and the anticipated spend for the three month extension is £33,477

RGE Services Ltd. The extended value of the Electrical Maintenance contract with this company is £435,384 and the anticipated spend for the three month extension is £18,930

Clearwater Technology Ltd. The extended value of the Water Treatment contract with this company is £1,104,316 and the anticipated spend for the three month extension is £48,014

Industrial Lifts Services Ltd. The extended value of the Lift Maintenance contract with this company is £255,605 and the anticipated spend for the three month extension is £11,113

Rentokil Initial Fire Services Ltd. The extended value of the Fire Fighting Equipment Maintenance contract with this company is £198,864 and the anticipated spend for the three month extension is £8,646

Extension of the above contracts will enable both cyclical and responsive maintenance works to be undertaken throughout the Council’s non-housing operational buildings from 1st January 2013 until 31st March 2013. 

Report author: Martyn Carter, Bruno de Souza

Publication date: 20/12/2012

Date of decision: 17/12/2012

Decided at meeting: 17/12/2012 - Cabinet Resources Committee

Effective from: 21/12/2012