Referral from Policy and Resources Committee to Full Council: Brent Cross Cricklewood Funding and Delivery Strategy Report

Decision Maker: Council

Decision status: Recommendations Approved

Is Key decision?: No

Is subject to call in?: No

Decisions:

Councillor Daniel Thomas, Chairman of the Assets, Regeneration & Growth Committee, moved reception and adoption of the recommendations in the report.  Debate ensued.

 

On the recommendations in the report being put to the vote, votes were recorded as follows:

 

For

35

Against

0

Abstentions

25

Absent

3

 

RESOLVED that:

 

1)    Given the strategic importance of BXC and the scale of the investment proposed in delivery of the new Thameslink station at Brent Cross West (BXT), Council confirm the council’s continuing commitment to the delivery of BXT and other elements of the critical infrastructure needed to support BXC.

 

2)    Council authorises the Deputy Chief Executive to enter into the Implementation Agreement with Network Rail and to commission the Schedule 1A (site set up) works set out in that agreement.

 

3)    Council delegate authority to the Policy & Resources Committee to commission the Schedule 1B (rail systems and sidings) works provided: (a) a Revised Funding Agreement (RFA) has been agreed with HM Government (HMG); and (b) that the RFA does not expose the council to unacceptable risk.

 

Publication date: 17/01/2019

Date of decision: 18/12/2018

Decided at meeting: 18/12/2018 - Council