Decision details
Highway Asset Management - Network Recovery Plan Whole Life Costing of Footway Maintenance Treatments
Decision Maker: Environment and Climate Change Committee
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: No
Purpose:
To note the highway asset management whole life costing
Decisions:
The Commissioning Director for Environment introduced the report, which explained the concept of whole life costing highway asset management, and referenced a “toolbox” of standardised construction designs.
Following a question from a Member, the Commissioning Director for Environment undertook to discuss gradients and crossovers with engineers in relation to whole life costing of footways.
Councillor Brian Salinger MOVED the following motion:
“That two more roads be tried out, with one that it is a typical road with crossovers, and one without crossovers so that Committee Members can consider that before taking any decisions in principle, and that the decision on whole life principles can be deferred.”
Votes were recorded as follows:
For |
11 |
Against |
0 |
Abstentions |
0 |
The motion was CARRIED and became the substantive motion.
The Committee RESOLVED to instruct that two more roads be tried out, with one that it is a typical road with crossovers, and one without crossovers so that Committee Members can consider that before taking any decisions in principle, and that the decision on whole life principles can be deferred.
Publication date: 24/02/2016
Date of decision: 11/01/2016
Decided at meeting: 11/01/2016 - Environment and Climate Change Committee
Accompanying Documents: