Issue - meetings
Page Street/Bunns Lane/Pursley Road - Junction Improvements
Meeting: 26/10/2016 - West Area Committee (Item 10)
10 Page Street/Bunns Lane/Pursley Road - Junction Improvements PDF 5 MB
Additional documents:
- Appendix A Cover Sheet, item 10 PDF 11 KB
- Appendix A – Feasibility Design Options, item 10 PDF 395 KB
- Appendix B, item 10 PDF 107 KB
- Appendix C Cover Sheet, item 10 PDF 14 KB
- Appendix C - Pedestrian Traffic Survey summary, item 10 PDF 415 KB
Minutes:
The Chairman reminded the Committee that this item had been discussed at the previous Committee in July and a decision deferred to enable Mill Hill Ward Councillors to meet to consider and agree the options.
Councillor Khatri following a request to provide his comments on the item expressed his concern that there should be further studies and consultations. Councillor Duschinsky commented that having four options to consider was too much and choosing between two options would be sufficient.
Officers, reporting back on the outcome of the initial feasibility study, described how the proposal was include developing detailed design for the four options, and at the meeting with Ward Councillors, they had requested for additional surveys to fully understand traffic movements.
Councillor Langleben said he was familiar with the issues affecting the route and recognised the benefits of additional surveys to help identify the best solution once and for all. There was a consensus amongst the Committee to allocate a maximum budget of £10,000 for additional feasibility works, the outcome of which should be reported to the Committee in January 2017.
It was RESOLVED that Committee:-
1. Noted the detail of the feasibility study as outlined in this report in relation to the Page Street / Bunns Lane / Pursley Road, NW7 double mini-roundabout junction.
2. Noted the detail of the feasibility study as outlined in this report in relation to the Page Street / Bunns Lane / Pursley Road, NW7 double mini-roundabout junction.
3. Having noted the above in 1 and 2, agreed the expenditure of a maximum of £10,000 from the Hendon Area Committee budget CIL to further design the Options to take account of the high level of pedestrian movements between the double mini roundabouts and the movement of vehicles through the junction, and gave an instruction to the Commissioning Director for Environment to design the proposed junction improvements at the Page Street/Bunns Lane/Pursley Road double mini-roundabout junction within the agreed £10,000budget.