Authorisation to sign Joint Contracts Tribunal (JCT) contract with Larkfleet/ Asset Plus for Public Sector Decarbonisation Scheme (PSDS3) works and Martin School Caretaker's Home decarbonisation works

Decision status: Recommendations Approved

Is Key decision?: No

Is subject to call in?: No

Decisions:

Councillor Alan Schneiderman Cabinet Member for Environment & Climate Change introduced the report.

 

Following discussion, the Chair moved to vote on the recommendations.

 

DECISION:

 

It was RESOLVED:

 

1.    That Cabinet approved increasing the value of the JCT contract by £1.1m so that total contract value is £10.1m (previously estimated in the Annual Procurement Forward Plan (APFP) presented to Policy and Resources Committee on 22 Feb 2023 as a £9m). This is to include additional PSDS3 project costs and decarbonisation works at Martin school caretaker’s house.

2.    That Cabinet approved signing JCT contract with Larkfleet/ Asset Plus, at a value of £10.1m, to complete energy efficiency works to Barnet-owned buildings, managed as part of the Public Sector Decarbonisation Scheme Phase 3 (PSDS3). And to install a heat pump, low surface temperature radiators, hot water cylinder heat pump and solar PV at Martin School caretaker’s home.

 

The report set out the options considered, if any, and the reasons for the recommendations and the decision.

 

Publication date: 18/04/2024

Date of decision: 18/07/2023

Decided at meeting: 18/07/2023 - Cabinet