Decision details

Brent Cross Cricklewood Regeneration: Brent Cross West - Waste Transfer Station Procurement Strategy

Decision Maker: Chief Executive

Decision status: Recommendations Approved

Is Key decision?: No

Is subject to call in?: No

Purpose:

In accordance with the ARG Committee approvals on 24 April and 27 November 2017, this report details the Procurement Strategy to deliver the Waste Transfer Station (WTS) as part of the Phase 1B (South) Thameslink Station Works being delivered by the Council to support the comprehensive regeneration of Brent Cross Cricklewood (BXC).  The Procurement Strategy recommends that Graham Construction as the strategic construction partner to deliver the facility and Conway Aecom through the London Highways Alliance Contract (LoHAC) framework to undertake the associated highways works.  The report also details the works required to commence in January 2018 to ensure that early works start in July 2018 and the main build contract in November 2018.  Commencement of works will be subject to a separate Delegated Powers Report.

 

Decision:

To procure Graham Construction as the Strategic Construction Partner to deliver the Waste Transfer Station (WTS) and Conway Aecom through the London Highways Alliance Contract (LoHAC) frameworkto undertake the associated highways works to deliver the WTS requirements subject to further authorisations as may be necessary as identified in this report.

Publication date: 06/02/2019

Date of decision: 18/01/2018

Accompanying Documents: