Brent Cross Cricklewood Regeneration
Decision status: For Determination
Is Key decision?: Yes
Is subject to call in?: Yes
Decisions:
For the reasons set out in the Cabinet Member’s report
RESOLVED
That Cabinet Resources Committee
a) approve the changes to the terms of the Brent Cross Principal Development Agreement (as considered and approved by CRC in October 2010) as set out in Section 9 of this report;
b) approve the terms for the Co-operation Agreement as set out in Section 9 of this report;
c) authorises the Chief Executive in consultation with the Leader of the Council to agree the detail of the Brent Cross Principal Development Agreement and Co-operation Agreement;
d) approve commencement of market testing through the issue of a Prior Information Notice to inform the delivery strategy for the Brent Cross Cricklewood South area;
e) approve that the Council enter into negotiations with landowners to acquire land required in advance of any Compulsory Purchase Order, subject to approval of the bid for capital funding by Cabinet on 25 February 2014;
f) approve that the Council continue the design and development work to develop the business case and funding strategy for delivery of the Thameslink Station, subject to approval of the capital funding bid by Cabinet on 25 February 2014;
g) delegate authority to the Strategic Director for Growth and Environment to procure the necessary advice and consultants to progress the Brent Cross project workstreams and deal with the related contractual issues and arrangements.
Publication date: 20/01/2014
Date of decision: 16/01/2014
Decided at meeting: 16/01/2014 - Cabinet Resources Committee
Effective from: 25/01/2014